Route 15 Ranchero Road Interchange Construction |
Description: In Hesperia, on Route 15, at Ranchero Road between Joshua Street and Oak Hill Road.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Hesperia |
Zip Code | 92345 |
Senate District |
17 |
Assembly District | 36 |
Congressional District | 41 |
Caltrans District |
08 |
County/State Route | San Bernardino 15 |
Postmile Begin/End | 29.5 30.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1400 | 957 |
Lane Miles Added (HOV) | 0 | 0 |
Lane Miles Added (Mixed) | 0 | 0 |
Peak Period Time Savings (minutes) | 21191 | 76,184 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Hesperia, City of | Barbara Fortman | (909)884-8276 | Bfortman@sanbag.ca.gov | |
Design (PS&E) Phase |
Hesperia, City of | Barbara Fortman | (909)884-8276 | Bfortman@sanbag.ca.gov | |
Right of Way Phase |
Hesperia, City of | Barbara Fortman | (909)884-8276 | Bfortman@sanbag.ca.gov | |
Construction Phase |
Hesperia, City of | Mike Barnum | (909)884-8276 | mbarnum@sanbag.ca.gov | |
Corridor System Management Plan |
San Bernardino Associated Governments | Barbara Fortman | (909) 884-8276 | anieto@sanbag.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $0 | $0 | ||||
CMIA |
$21,135 | $7,129 | $28,264 | ||||
SLPP |
$4,550 | $0 | $4,550 | ||||
Non-bond Funding | |||||||
State/Federal* |
$17,521 | $-7,479 | $10,042 | ||||
Local** |
$21,140 | $-73 | $21,067 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $64,346 | $-423 | $63,923 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,005 | $0 | $1,005 | $1,396 | |||
Design(PS&E) |
$3,570 | $0 | $3,570 | $3,496 | |||
Right of Way |
$15,550 | $0 | $15,550 | $12,084 | |||
Construction |
$44,221 | $-423 | $43,798 | $41,620 | |||
Total* | $64,346 | $-423 | $63,923 | $58,596 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
08/01/2007 03/18/2010 |
|
08/01/2007 03/18/2010 |
100 | 08/01/2007 03/18/2010 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2008 05/18/2012 |
|
11/01/2008 05/18/2012 |
100 | 11/01/2008 05/21/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
03/18/2010 05/18/2012 |
|
03/18/2010 05/18/2012 |
100 | 03/18/2010 05/15/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/01/2012 08/01/2014 |
|
08/01/2012 08/01/2014 |
100 | 11/01/2012 12/18/2015 |
-3 -17 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2014 09/01/2016 |
|
09/01/2014 09/01/2016 |
75 | 12/22/2015 06/30/2021 |
-16 -59 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2011 | 10/01/2011 | 0 | 10/01/2011 | 0 | ||
Implementation Date | 10/01/2011 | 10/01/2011 | 0 | 10/14/2011 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1400 | 957 |
Lane Miles Added (HOV) | 0 | 0 |
Lane Miles Added (Mixed) | 0 | 0 |
Peak Period Time Savings (minutes) | 21191 | 76,184 |
Bond Funding Cost | |
---|---|
Adopted: |
$25,685,000 |
Current Approved: |
$28,614,000 |
Actual Expenditures: |
$27,480,000 |
Status as of December 31, 2023.